1
141
1977 A.D. Little SPS Effects On Electric Industry
JPL Cover Page
1
Distribution List
2
Report Cover
4
Report Letter
5
Table of Contents
6
List of Figures
8
Fig 1.1 Required Percent Installed Margin As A Function of the Power Pool Size - 1 SPS
23
Fig 1.2 Required Perecent Installed Mrgin As A Function of the Power Pool Size - 2 SPSs
24
FIg 1.3 Required Perecent Installed Mrgin As A Function of the Power Pool Size - 6 SPSs
25
Fig 2.1 National Electric Reliability Council
35
Fig 2.2 Frequency Distribution As A Function of TIme After Perturbation
41
Fig 2.3 Transmitted Power as a Function of the Generator Power Angle
44
Fig 2.4 Diagram of Load Control Areas and Power System Interconnections
47
Fig 2.5 Demand for Power In the Two Power Consuming Elements of the Composite Power Pool as a Function of the Time-Of-Da
57
Fig 2.6 Required Percent Installed Margin as a Function of the Power Pool Size - 1 SPS
58
Fig 2.7 Required Percent Installed Margin as a Function of the Power Pool Size - 2 SPSs
59
Fig 2.8 Required Percent Installed Margin as a Function of the Power Pool Size - 6 SPSs
60
Fig 2.9 Demand For Power From Conventional Generators In The West Coast Component of the Composite Power Pool as a Function of Time
69
Fig 3.1 Demand for Electric Power Over A Weekly Cycle
77
Fig 3.2 Power Demand as a Function of Time - 5% Growth Rate
79
FIg 3.3 Power Demand as a Function of Time - 5% Growth Rate
80
Fig 3.4 Avereage Fuel Fixed and Total Pre Unit Costs
89
Fig 3.5 Average Per Unit Fuel Costs FIxed Costs and Total Costs
90
Fig 3.6A Total Debt As A Function of Time
101
Fig 3.6B Debt Incurred Yearly as a Function of Time
101
Fig 3.7A Total Debt as a Function of Time
102
Fig 3.7B Bebt Incurred Yearly as a Function of Time
102
List of Tables
10
1.1 Installed Generating Margin (GWe)For the Various Pools as a Function of the Circumstances
21
2.1 Regional Load Density (1974) (contiguous U.S. only)
34
2.2 Required Installed Generating Margin (GWe) For a Range of Power Pools According to Various Circumstances
55
3.1 Incremental Costs of Conventional Generation
96
3.2 Maximum Allowed Discount Rate As a Function of Inflation Revenues Set Equal to Fuel Costs of Nuclear Generator
97
3.3 Maximum Allowed Discount Rate as a Function of Inflation Revenues Set Equal to Fuel Costs of Coal Generators
97
3.4 Maximum Allowed Discount Rate as a Function of Inflation Revenues Set Equal to Fuel Costs of Oil Generators
98
3.5 Year _D Becomes Negative as a Function of Inflation - v Nuclear
99
3.6 Year _D Becomes Negative as a Function of Inflation - v Coal
100
3.7 Year _D Becomes Negative as a Function of Inflation - v Oil
100
A.1 Length of Time (Hours) Power Demand Between m and m-1 GWe - 30GWe Pool
120
A.2 Length of Time (Hours) Power Demand Between m and m-1 GWe - 40GWe Pool
121
A.3 Length of Time (Hours) Power Demand Between m and m-1 GWe - 50GWe Pool
122
A.4 Length of Time (Hours) Power Demand Between m and m-1 GWe - Composite Pool
124
A.5 Required Number of Conventional Generators in a 30 GWe Power Pool as a Function of Maintenance Interval and Circumstances
126
A.6 Required Number of Conventional Generators in a 40 GWe Power Pool as a Function of Maintenance Interval and Circumstances
127
A.7 Required Number of Conventional Generators in a 50 GWe Power Pool as a Function of Maintenance Interval and Circumstances
128
A.8 Required Number of Conventional Generators in Each Portion of the Composite Power Pool (30 GWe and 30 GWe) as a Function of Maintenance Interval and Circumstances
133
Introduction and Summary
12
1.1 Executive Summary
12
1.2 Reliability and Stability
16
1.3 Possible Ownership of the SPS
26
1.4 Utility Participation in SPS Related RD&D
30
1.5 Utility Liabilities Associated with the SPS
30
1.6 Structure of the Report
31
2.0 Reliability and Stability
32
2.1 Background
32
2,2 Power System Stability Characteristics
37
2.2.1 Introduction and Results
37
2.2.2 System Dynamics
38
2.2.3 Protection Devices
43
2.2.4 Northeast Blackout
46
2.3 Power Pool Reliability
50
2.3.1 Introduction and Summary
50
2.3.2 Formulation of the Problem
61
2.3.2.1 Definitions
61
2.3.2.2 Power Pool Loads
65
2.3.2.3 Number of Required Generators
68
3.0 Possible Ownership of SPS
72
3.1 Introduction
72
3.1.1 Summary
72
3.1.2 General Financial Characteristics of the Generation Mix
76
3.2 Purchase of the SPS by a Utility or Consortium of Utilities
85
3.3 "Leasing" the SPS
92
3.4 Pricing SPS Produced Energy at the Incremental Cost of Alternative Generation
94
3.4.1 Introduction
94
3.4.2 Calculated Maximum Discount Rates
95
4.0 Utility Participation in the SPS RD&D Programs
103
5.0 Utility Liability Due to the Adverse Effects of SPS Related Activities
107
Appendix A: Calculation of the Power Pool Genreating Margins Required To Meet the LOLP Criteria
113
Appendix B: Change In Power Pool Due to SPS
134
Appendix C: Cash Flow Analysis - SPS Energy Prices At The Cost of Alternative Base Load Generation
137
RkJQdWJsaXNoZXIy MTU5NjU0Mg==