The task timelines show tasks as horizontal bars that span elapsed time for a task or a milestone. The bars are lined out in chronological order. Super tasks have a half-oval at each end of the bar for planned duration. A milestone that has no duration appears as a diamond. Tasks appear as simple bars. The white portions of the bars symbolize the duration of a task. The shaded portions of the bars symbolize the slack.