Technical, Environmental, Economic Evaluation of SPS V1 Summary

Cover 1
Title Page 3
Table Of Contents 5
List of Tables 9
TABLE IV-1. - A SUMMARY OF MICROWAVE SYSTEM(S) PARAMETERS 30
TABLE IV-2. - SUMMARY OF UNIT MASSES 36
TABLE IV-3. - MASS PROPERTIES SUMMARY 38
TABLE IV-4. - COST ESTIMATING RELATIONSHIPS 56
TABLE V-l. - ORBITAL CONSTRUCTION EQUIPMENT REQUIREMENTS 69
TABLE V-2. - COLUMN/CABLE CONFIGURATION TYPICAL MAN LOADING 70
TABLE V-3. - TRUSS CONFIGURATION TYPICAL MAN LOADING (GEO CONSTRUCTION) 71
TABLE V-4.- TYPICAL PEAK STAFFING (LEO) FOR ANTENNA SUBARRAY FABRICATION 72
TABLE VI-1 - HLLV CANDIDATE ENGINE CHARACTERISTICS 75
TABLE VI-2. - HLLV CANDIDATE CONFIGURATION CHARACTERISTICS 75
TABLE VI-3.- HLLV COST ESTIMATES 78
TABLE VI-4. - OTV CANDIDATE THRUSTER CHARACTERISTICS 82
TABLE VI-5. - HLLV RANGE OF PROJECTED ESTIMATES 90
TABLE VI-6. - PLV RANGE OF PROJECTED ESTIMATES 90
TABLE VI-7. - COTV RANGE OF PROJECTED ESTIMATES 91
TABLE VI-8. - POTV RANGE OF PROJECTED ESTIMATES 91
TABLE VI-9. - RELATIVE TRANSPORTATION COSTS FOR SEVERAL SPS CONFIGURATIONS AND CONSTRUCTION LOCATIONS 92
TABLE VII-1. - SPS PROGRAM MODEL INPUTS, ASSUMPTIONS, AND GUIDELINES 96
TABLE VII-2. - PROGRAM MODEL SUMMARY FOR "COLUMN/CABLE" SPS IN GEO 98
TABLE VII-3. - PROGRAM MODEL SUMMARY FOR "TRUSS" SPS IN GEO 100
TABLE VI1-4. - PROGRAM MODEL SUMMARY FOR "TRUSS" SPS IN LEO 102
TABLE VIII-1. - ENVIRONMENTAL COMPARISON OF 1O-GW POWERPLANT OPERATIONS 111
TABLE IX-1, - NATURAL RESOURCE DEMANDS OF A 10-GW SPS COMPARED TO NATIONAL AND WORLD DEMANDS IN THE YEAR 2OQO 114
TABLE IX-2. - ENERGY PAYBACK OF A 10-GW SPS 114
TABLE XI-1. - DDT&E COST ESTIMATE SUMMARY 129
TABLE XI-2.- SUMMARY OF COST ESTIMATES AND RELEVANT PARAMETERS FOR 1O-GW SPS 129
List of Figures 11
Figure I-1.- Study task structure. 18
Figure III-l.- Projections of U.S. electrical energy requirements and possible SPS implementation scenarios 24
Figure IV-1.- SPS functional description 25
Figure IV-2.- Estimated efficiencies of the various steps in the collection, conversion, and transmission process. 27
Figure IV-3.- Output power limits. 28
Figure IV-4.- Power density at rectenna. 31
Figure IV-5.- Eclipse geometry 32
Figure IV-6.- Example configurations. 34
Figure IV-7.- Solar power satellite total mass 37
Figure IV-8.- Solar concentrator. 40
Figure IV-9.- Solar cell blanket 41
Figure IV-10.- Gravity gradient torques. 43
Figure IV-11.- Counterweight location 44
Figure IV-12.- Antenna element 48
Figure IV-13.- Typical antenna distribution system 49
Figure IV-14.- Antenna primary structure 50
Figure IV-15.- Ball joint and drive concept 51
Figure IV-16.- Rectenna construction. 53
Figure IV-17.- Variation in ground de power output. 54
Figure IV-18.- Photovoltaic array cost projection. 57
Figure V-1.- Beam builder machine concept. 59
Figure V-2.- Typical SPS construction sequence - column/cable (POP). 60
Figure V-3.- Partial construction of column/cable configuration 61
Figure V-4.- Concept for solar cel 1/concentrator deployment. 62
Figure V-5.- Construction base concept for truss configuration 63
Figure V-6.- Typical SPS construction sequence - truss configuration 64
Figure V-7.- Construction base concept for column/cable configuration 65
Figure V-8.- Operational schematic of construction base (column/cable). 68
Figure VI-1.- Modified single-stage-to-orbit launch vehicle 76
Figure VI-2.- Two-stage winged launch vehicle 77
Figure VI-3.- Two-stage ballistic launch vehicle. 79
Figure VI-4.- Personnel and priority cargo launch vehicle. 81
Figure VI-5.- LEO-to-GEO transfer time as a function of thrust/weight. 83
Figure VI-6.- Propellant burden contribution for high-thrust Og/Hz COTV 85
Figure VI-7.- Cargo orbital transfer vehicle (COTVg) characteristics 86
Figure VI-8.- Crew module concept. 87
Figure VI-9.- Crew rotation passenger module. 88
Figure VII-10.-Personnel orbital transfer vehicle (POTV|J characteristics. 89
Figure VII-1.- SPS mission scenario 94
Figure VII-2.- SPS mission management concept. 104
Figure X-l.- Space solar power projected program phasing. 117
Figure X-2.- System definition and exploratory technology phase activities 118
Figure X-3.- The relative merits of space solar power and other systems - coal, nuclear, solar terrestrial 121
Figure X-4.- Significant test activities, initial phase, July 1976 to July 1978 (partial listing) 121
Figure X-5.- Technology advancement phase. 122
Figure XI-1. - Cost Estimates 127
Figure XI-2.- SPS cost parametrics. 130
Figure XI-3.- Conventional and advanced power generation system costs. 131
Figure XI-4.- Terrestrial solar power. 132
Figure XI-5.- The 5-GW solar power tower concept with electrolysis cell/fuel cell energy storage 133
Figure XI-6.- The 5-GW solar photovoltaic-fuel cel1/electrolysis cell system. 133
Figure XI-7.- Terrestrial solar photovoltaic power cost for 5-GW plant 134
Figure XI-8.- Terrestrial solar thermal power cost for 5-GW power tower concept. 135
Figure XI-9.- Land area requirements for 5-GW plant 136
Figure XI-10.- Satellite cost breakdown 137
I. Introduction 15
II. Conclusions 19
III. Program Requirements 23
A. Projected Energy Demand 23
B. Implementation Scenarios 23
IV. Power Station 25
A. System Analysis 26
1. Efficiencies 26
2. MPTS/MRCS Analysis 26
3. Orbit Considerations 29
4. Configurations 33
5. Mass Properties 35
B. Solar Energy Collection System 39
1. Solar Array 39
2. Power Distribution 41
3. Structure 42
4. Attitude and Orbit Control 43
5. Instrumentation, Control, and Communications 45
6. Maintenance Station 45
C. Microwave Power Transmission System 46
1. Antenna Array 46
2. Microwave Generators 46
3 .Subarrays 46
4. Phase Control 47
5. Pointing Control 47
6. Power Distribution 49
7. Structure 50
8. Rotary Joint 50
9. Thermal Control 52
D. Microwave Reception and Conversion System 52
1. Rectenna 52
2. Grid Interface 53
E. Operations 53
F. Unit Costs 55
V. SPS Construction and Maintenance System 59
A. System Requirements and Analysis 59
B. Construction Base 63
1. Construction and manufacturing facility 64
2. Orbital construction and support equipmen 66
3. Logistics facility 66
4. Integration management facility 66
5.Crew habitability facilities 67
C. Construction Operations 67
VI. Space Transportation Systems 73
A. Systems Requirements and Analysis 73
B. Heavy Lift Launch Vehicle 74
C. Personnel and Priority Cargo Launch Vehicle 80
D. Cargo Orbital Transfer Vehicle 80
E. Personnel Orbital Transfer Vehicle 84
F. A Summary of Projected Transportation System Characteristics 89
VII. Integrated Operations 93
A. Systems Requirements Analysis 93
B. Program Model 93
C. Mission Management Concept 95
D. Mission Management Functions 95
1. Program Headquarters Mission Control 95
2. Launch and Recovery Control 104
3. LEO Operational Base Control 105
4. GEO Operational Base Control 105
5. SPS (Individual Unit) Ground Control 106
E. Key Considerations and Areas For Further Investigation 106
1. Prelaunch, Launch, and Recovery Operations 106
2. Space Manufacturing and Construction Options 107
3. Operational Space Base Control Operations 107
4. Simulation and Training Operations 107
5. Safety in SPS Operations 108
VIII. Environmental Considerations 109
A. Methodology 109
B. Environmental Questions 109
C. Comparisons With Conventional Systems 110
IX. Manufacturing Capacity, Natural Resources, Transportation and Energy Considerations 113
A. Requirements 113
B. Manufacturing Capacity 113
C. Natural Resources 113
D. Surface Transportation 113
E. Energy Payback 115
X. Program Development Plan 117
A. Program Phasing 117
B. System Definition and Exploratory Technology Phase 117
C. Technology Advancement Phase 122
D. System Development 123
E. Program Costs 123
XI. Program Cost and Economic Analysis 125
A. Methodology 125
B. SPS Costs 125
C. Comparison With Conventional and Other Advanced Systems 128
D. Summary Remarks 134

RkJQdWJsaXNoZXIy MTU5NjU0Mg==