NASA 2024 Space-Based Solar Power

59 Results Total SBSP Lifecycle Costs Table 15. Costs by Capital Expenditures and Fixed Operations and Management SBSP Lifecycle Costs by ConOps Phase Table 16. SBSP Lifecycle Costs for the Develop ConOps Phase Table 17. SBSP Lifecycle Costs for the Assemble ConOps Phase Cost Estimate Results (FY22$) RD1 Baseline ($) RD2Baseline ($) Launch of Original Hardware 65.19B 111.6B Servicer Manufacturing 10.89B 9.86B Mission Program Management, Systems Engineering, and Mission Assurance 2.7B 2.46B ConOps Phase RD1 ($) RD2 ($) CapEx Develop 11.65B 12.95B Assemble 78.9B 124.1B Total $90.57B $137B FOM Operate 3.79B 9.36B Maintain 157.1B 248.85B Dispose 24.7B 38.94B Total $185.65B $297.17B Total $276.2B $434.2B Cost Estimate Results (FY22$) RD1 Baseline ($) RD2 Baseline ($) Mission Program Management, Systems Engineering, and Mission Assurance 2.33B 2.59B Technology Development 2.4B 2B Spacecraft Hardware 6.9B 8.29B Develop Total 11.65B 12.95B